    If I have AX 2012 R3 CU9 and needs to be upgraded to the latest version.

    Do we have to upgrade to the next CU 10 then 11 one by one until we reach to the latest? Or directly we can upgrade to the latest one?

    #20893

    Locus IT
    Participant

    Hello Paul,

    You can directly upgrade to the latest version, which is CU13. These updates are cumulative. So there is no need to implement the other ones.

    #20889

    Anne Smith
    Participant

    Hi Paul,

    You can directly upgrade the version and I have already done same process like you, but when you upgrade application version you should check full compile, because you may face some errors if you have any customization in the AOT.